Wednesday, October 7, 2026

Broadcast Regulatory & Engineering Update - October 7, 2026

 

TZSTC Broadcast Regulatory & Engineering Update

October 7, 2026

FM Translator and LPFM Minor-Change Freeze Now in Effect

The FCC's temporary filing freeze on minor modification applications for LPFM stations, FM translators, and FM boosters took effect at 11:59 p.m. ET on October 2. The freeze will remain in place through the close of the upcoming reserved-band NCE FM translator filing window on November 17. FCC Docs

The first-ever filing window for new NCE FM translators on Channels 201–220 opens November 4 and closes at 6:00 p.m. ET November 17. The FCC has stated that the closing deadline will be strictly enforced, and November 17 will also be the comparative “snapshot” date for applications filed during the window. FCC Docs

TZSTC takeaway: Existing translator and LPFM operators generally cannot file routine technical modifications during the freeze. Applicants planning November NCE translator filings should have channel studies, sites, ownership information and application certifications substantially complete before the window opens.

FCC Significantly Revises Environmental Review Requirements

The FCC adopted a major revision of its National Environmental Policy Act (NEPA) procedures on September 30, releasing the final order October 1. For broadcast facilities, the principal practical change is that FCC environmental review will generally be tied to construction involving a new tower that requires Antenna Structure Registration (ASR) rather than being triggered simply because an FCC spectrum authorization is involved. FCC ID

The Commission is separately seeking further comment on its related historic-preservation procedures under the National Historic Preservation Act, so broadcasters should not assume that all tower-related federal review requirements have disappeared. FCC ID

TZSTC takeaway: This should simplify the regulatory path for many broadcast facility changes using existing structures or towers that do not require ASR. Historic-preservation, RF exposure, FAA/ASR and other applicable requirements remain separate considerations.

New EAS Cybersecurity Rules Are in Force

FCC cybersecurity requirements for EAS participants became effective September 29. Stations must change default passwords, use appropriate password security, promptly install security-related software and firmware updates, and protect remotely accessible EAS, STL and program-chain equipment with firewalls or comparable network segmentation. FCC Docs

TZSTC takeaway: Stations should review actual EAS and remote-control installations rather than assume that being “behind the station firewall” by itself establishes compliance. Older equipment that cannot support appropriate security may require additional protection or replacement planning.

Dates to Watch

October 13 — Quarterly Issues/Programs Lists due in the online public inspection file for full-power radio and television stations and Class A television stations. Michigan Association of Broadcasters

October 30 — All EAS participants must file 2026 ETRS Form One. FCC Docs

November 4–17 — NCE reserved-band FM translator filing window. FCC Docs

November 17 at 2:20 p.m. ET — Nationwide EAS test. ETRS Form Two will then be due by 2:20 p.m. ET November 19. FCC Docs